Description of project, activities & mission
Project operated by 8,2 AG x Dolfines
Ensure gearboxes and drivetrain/powertrain assemblies meet quality and compliance standards for the He Dreiht offshore wind farm.
- Documentation Review
- Visual Inspections
- Dimensional Checks & Functional Testing
- Assembly Verification
- Maintain detailed records of inspections, tests, and measurements.
- Document non-conformities and corrective actions.
- Conduct comprehensive final inspections.
- Provide approval and summary reports of inspection results.
The Dolfines group has experts providing a continuous presence at the various execution points around the north sea