OUR PROJECTS – CASE STUDY – Oil & Gas

SHWE project

DETAILS

Client name: DAEWOO INTERNATIONAL / HYUNDAI HEAVY INDUSTRIES
Project name: SHWE project
Duration: 10000 man-days

Project Description

DAEWOO INTERNATIONAL was developing the SHWE gas field, offshore Myanmar.
The objective of the project was to design an integrated jacket platform with drilling and production equipment and 200 beds living quarters. HHI missioned DORIS ENGINEERING to perform the design of the topside and DOLFINES was in charge of the basic and detailed design of the 3000HP platform rig.

Activities / Tasks and Solutions developed by Dolfines

DORIS ENGINEERING and DOLFINES performed together the basic and the FEED design of both the topside and the platform rig. DOLFINES send an integrated engineering team to work within the offices of DORIS ENGINEERING. A support team of DOLFINES has also been sent to the HHI yard in Ulsan, South Korea, during the detailed engineering

Project Results

The engineering phase has been done from 2008 to 2010, in France and in South Korea. All the engineering documents have been produced an issued to the client for the detailed engineering.
The topside has been manufactured in Korea and has been successfully assembled to the jacket in November 2012.
The first gas has been produced in July 2013.